How to calculate a project end date from a duration in working days in Excel

Formula (Excel and Google Sheets)

=WORKDAY(B2,C2-1,$F$2:$F$3)

Count the duration minus one working day from the start: =WORKDAY(B2,C2-1,holidays), so the start day counts as day 1.

Result on the example
one result per row in D2, filled down to D6
Works in
Every current version
Google Sheets
Same formula

See it work

The formula is already in D2, filled down to D6. Change any input and the result updates, or edit the formula to experiment.

How it works

A task that starts on a working day and lasts 10 working days ends 9 working days later, so the formula adds C2-1. WORKDAY skips weekends and the holidays in F2:F3: the Build task runs over Memorial Day and ends a day later because of it.

=WORKDAY(B2,C2-1,$F$2:$F$3)

Result5/15/2026 (46157)

  1. B25/4/2026

    The value in B2.

  2. C210

    The value in C2.

  3. C2-19

    The - operator subtracts.

  4. $F$2:$F$32 rows × 1 col: 5/25/2026, 7/3/2026

    A range: 2 cells in one column.

  5. WORKDAY(B2,C2-1,$F$2:$F$3)5/15/2026 (46157)

    WORKDAY: Date a number of workdays away.

    • start_dateB25/4/2026
    • daysC2-19
    • holidays$F$2:$F$32 rows × 1 col: 5/25/2026, 7/3/2026

In Google Sheets

The same formula works in Google Sheets: =WORKDAY(B2,C2-1,$F$2:$F$3). We ran it in Google Sheets mode on the same data and it returns the same results.

Other ways to do it

Each one was run on the same example sheet.

FormulaResultWhen to use it
=WORKDAY(B2,C2,$F$2:$F$3)5/18/2026, 6/9/2026, 7/7/2026…Different resultCounts the whole duration after the start day. One working day later.

Common mistakes

  • =WORKDAY(B2,C2) doesn't count the start day, so every task ends a day late.
  • A start date on a weekend still counts as day 1. Move starts to a weekday first.

Try it yourself

Same data, empty answer cell. Your formula is graded instantly, then re-checked on changed data, so a typed-in number won't pass.

Calculate a project end date from a duration in working days

In D2, calculate the last working day of each task, counting the start date as day 1 and skipping weekends and the holidays in F2:F3. Fill down to D6.

Questions

How do I calculate the duration from start and end dates?

=NETWORKDAYS(B2,D2,$F$2:$F$3) counts both ends.

How do I start the next task the day after?

=WORKDAY(D2,1,$F$2:$F$3) returns the next working day.