WORKDAY function

WORKDAY returns the date a given number of working days before or after a start date, skipping weekends and any holidays you list. Use it for ship dates, deadlines and follow-up dates that must land on a business day. The start date itself is not counted.

Available in
Every current version
Category
Date functions
Returns
A date serial number. Format the cell as a date.
Google Sheets
Works the same in Google Sheets.

Syntax

=WORKDAY(start_date, days, [holidays])

ArgumentRequired?What it is
start_dateRequiredThe date to count from. It isn't counted as one of the days.
daysRequiredHow many working days to move. Negative numbers count backward.
holidaysOptionalAn optional range of dates to skip.

Examples

Each result below is calculated from the sample sheet by our formula engine, the same one that grades the practice.

CellFormulaResultWhat it shows
F2=WORKDAY(A2,B2)Nov 27, 2026Three working days after Tuesday, November 24
F3=WORKDAY(A2,B2,D2:D4)Dec 1, 2026Skipping Thanksgiving and the day after pushes it to December 1
F4=WORKDAY(A3,B3,D2:D4)Dec 28, 2026Christmas Day and the weekend push this one to December 28

Try it live

This is the sample sheet. Change any number or text, or edit a formula, and the results update.

Show the sample data as a table
Order dateDaysHolidaysResult
11/24/2026311/26/2026Nov 27, 2026
12/23/2026211/27/2026Dec 1, 2026
12/25/2026Dec 28, 2026

Practice WORKDAY

Graded instantly, then re-checked on changed data.

Ship dates

In C2, calculate each ship date: the order date plus the processing days, skipping weekends and the holidays in E2:E4. Fill down to C6.

Common mistakes

What you seeWhy, and how to fix it
A five-digit number instead of a dateWORKDAY returns a serial number. Format the cell as a date.
The deadline is a day lateThe start date doesn't count. WORKDAY(A2,1) is the next working day, not A2 itself.
Holidays are ignored after filling downThe holiday range shifted. Lock it with $: $D$2:$D$4.

Tips

  • Use a negative number of days to find when work must start: =WORKDAY(deadline,-10).

Questions

How do I add business days to a date in Excel?

Use =WORKDAY(A2,10) to move 10 working days forward, skipping weekends. Add a holiday range as the third argument.

Does WORKDAY count the start date?

No. It starts counting from the next working day, so WORKDAY(A2,1) is the first business day after A2.

Can WORKDAY skip a different weekend, like Friday and Saturday?

Not WORKDAY itself. WORKDAY.INTL takes a weekend argument for that.

Last reviewed October 2026. Every example result on this page is calculated live by the Spreadsheet Practice formula engine.