How to calculate the number of days until a deadline in Excel

Formula (Excel and Google Sheets)

=B2-$F$1

Subtract today's date from the deadline: =B2-$F$1, with today's date in F1. Past deadlines come out negative.

Result on the example
one result per row in C2, filled down to C7
Works in
Excel 2013 and later
Google Sheets
Same formula

See it work

The formula is already in C2, filled down to C7. Change any input and the result updates, or edit the formula to experiment.

How it works

Subtracting today from the deadline gives the days still to go, and a negative result tells you how many days late it is. F1 holds the date to count from; put =TODAY() there to make the sheet live, or type a date to see the plan as of that day.

=B2-$F$1

Result18

  1. B211/16/2026

    The value in B2.

  2. $F$110/29/2026

    The value in F1.

  3. B2-$F$118

    The - operator subtracts.

In Google Sheets

The same formula works in Google Sheets: =B2-$F$1. We ran it in Google Sheets mode on the same data and it returns the same results.

Other ways to do it

Each one was run on the same example sheet.

FormulaResultWhen to use it
=MAX(0,B2-$F$1)18, 33, 0…Different resultShows 0 instead of a negative number once the deadline has passed. Past deadlines show 0.
=DAYS(B2,$F$1)18, 33, 0…The same result with DAYS. Note the order: deadline first.
=NETWORKDAYS($F$1,B2)-112, 23, 0…Different resultWorking days left, not counting today. Counts Monday to Friday only.

Common mistakes

  • With B2-TODAY() in every row the numbers change each day and can't be checked later. A single "today" cell is easier to audit and to test.
  • If the result shows as a date, format the column as a number.
  • A deadline with a time, like 5:00 PM, gives a fraction. Use INT(B2) in the subtraction.

Try it yourself

Same data, empty answer cell. Your formula is graded instantly, then re-checked on changed data, so a typed-in number won't pass.

Calculate the number of days until a deadline

In C2, calculate how many days are left until each deadline, counting from the date in F1. Fill down to C7.

Questions

How do I show "Overdue" instead of a negative number?

=IF(B2<$F$1,"Overdue",B2-$F$1&" days left").

How do I count only business days left?

=NETWORKDAYS($F$1,B2,holidays)-1 skips weekends and holidays and leaves out today.

Checked by running on 2026-10-30: every formula and result on this page was calculated by the Spreadsheet Practice formula engine, in both Excel and Google Sheets modes.