NETWORKDAYS.INTL function

Quick answer

NETWORKDAYS.INTL counts the working days between two dates, like NETWORKDAYS, but lets you say which days are the weekend: Friday and Saturday, Sunday only, or any pattern written as a seven-character string such as "0000011".

Syntax
=NETWORKDAYS.INTL(start_date, end_date, [weekend], [holidays])
Most common use
=NETWORKDAYS.INTL(A2,B2) returns 22 (Monday to Friday in March 2026: 22)

Use it for teams, countries or shifts that don't work Monday to Friday.

Available in
Excel 2010 and later
Category
Date functions
Returns
A whole number of working days; negative if the end date is before the start.
Google Sheets
Works the same in Google Sheets.

Syntax

=NETWORKDAYS.INTL(start_date, end_date, [weekend], [holidays])

ArgumentRequired?What it is
start_dateRequiredThe first day of the period.
end_dateRequiredThe last day. Both count when they are working days.
weekendOptionalOptional: a code (1 Saturday–Sunday, 7 Friday–Saturday, 11 Sunday only, 17 Saturday only…) or seven 0s and 1s from Monday to Sunday, 1 for days off.
holidaysOptionalOptional: a range of dates to skip.

Examples

Each result below is calculated from the sample sheet by our formula engine, the same one that grades the practice.

CellFormulaResultWhat it shows
E2=NETWORKDAYS.INTL(A2,B2)22Monday to Friday in March 2026: 22
E3=NETWORKDAYS.INTL(A2,B2,7)23Sunday to Thursday, with Friday and Saturday off: 23
E4=NETWORKDAYS.INTL(A2,B2,"0000011",C2)21Saturday and Sunday off, written as a string, minus the holiday: 21

Try it live

This is the sample sheet. Change any number or text, or edit a formula, and the results update.

Show the sample data as a table
StartEndHolidayResult
3/1/20263/31/20263/20/202622
23
21

Practice NETWORKDAYS.INTL

Graded instantly, then re-checked on changed data.

Six-day weeks

The warehouse works Monday to Saturday. In D2, count the working days from A2 to B2, with Sunday the only day off and the holidays in F2:F3 excluded. Fill down to D6.

Common mistakes

What you seeWhy, and how to fix it
#VALUE!The weekend string isn't seven characters of 0 and 1, or every day is marked as weekend.
#NUM!The weekend code isn't one of 1–7 or 11–17.
One day too manyBoth the start and end dates count when they are working days.

Tips

  • Read a weekend string from Monday to Sunday: "0000011" means Saturday and Sunday off.

Questions

How do I count working days with a Friday–Saturday weekend?

=NETWORKDAYS.INTL(A2,B2,7). Code 7 marks Friday and Saturday as the weekend.

How do I count Mondays to Saturdays?

Use 11, Sunday only: =NETWORKDAYS.INTL(A2,B2,11).

Updated Checked by running: every formula on this page was run by our formula engine on .