# WORKDAY function in Excel

> WORKDAY returns the date a given number of working days before or after a start date, skipping weekends and any holidays you list.

Source: https://spreadsheetpractice.com/functions/workday · Updated October 28, 2026 · Formulas and results on this page were run by the Spreadsheet Practice formula engine on November 20, 2026

## Quick answer

- **What it does:** WORKDAY returns the date a given number of working days before or after a start date, skipping weekends and any holidays you list.
- **Syntax:** `=WORKDAY(start_date, days, [holidays])`
- **Most common use:** `=WORKDAY(A2,B2)` returns Nov 27, 2026 (Three working days after Tuesday, November 24)
- **Available in:** Every current version
- **Category:** [Date functions](https://spreadsheetpractice.com/functions/category/date)
- **Returns:** A date serial number. Format the cell as a date.
- **Google Sheets:** Works the same in Google Sheets.

## What it does

WORKDAY returns the date a given number of working days before or after a start date, skipping weekends and any holidays you list. Use it for ship dates, deadlines and follow-up dates that must land on a business day. The start date itself is not counted.

## Syntax

`=WORKDAY(start_date, days, [holidays])`

| Argument | Required? | What it is |
|---|---|---|
| `start_date` | Required | The date to count from. It isn't counted as one of the days. |
| `days` | Required | How many working days to move. Negative numbers count backward. |
| `holidays` | Optional | An optional range of dates to skip. |

## Examples

Each result was calculated by running the formula on the sample sheet.

| Cell | Formula | Result | What it shows |
|---|---|---|---|
| F2 | `=WORKDAY(A2,B2)` | Nov 27, 2026 | Three working days after Tuesday, November 24 |
| F3 | `=WORKDAY(A2,B2,D2:D4)` | Dec 1, 2026 | Skipping Thanksgiving and the day after pushes it to December 1 |
| F4 | `=WORKDAY(A3,B3,D2:D4)` | Dec 28, 2026 | Christmas Day and the weekend push this one to December 28 |

### The sample sheet

Every formula above runs on this data:

|  | A | B | C | D | E | F |
|---|---|---|---|---|---|---|
| 1 | Order date | Days |  | Holidays |  | Result |
| 2 | 11/24/2026 | 3 |  | 11/26/2026 |  | Nov 27, 2026 |
| 3 | 12/23/2026 | 2 |  | 11/27/2026 |  | Dec 1, 2026 |
| 4 |  |  |  | 12/25/2026 |  | Dec 28, 2026 |

## Common mistakes

| What you see | Why, and how to fix it |
|---|---|
| A five-digit number instead of a date | WORKDAY returns a serial number. Format the cell as a date. |
| The deadline is a day late | The start date doesn't count. WORKDAY(A2,1) is the next working day, not A2 itself. |
| Holidays are ignored after filling down | The holiday range shifted. Lock it with $: $D$2:$D$4. |

## Tips

- Use a negative number of days to find when work must start: =WORKDAY(deadline,-10).

## Related functions

- [NETWORKDAYS](https://spreadsheetpractice.com/functions/networkdays): NETWORKDAYS counts the working days between two dates, Monday to Friday, including both the start and end date.
- [EDATE](https://spreadsheetpractice.com/functions/edate): EDATE returns the date a given number of months before or after a start date, keeping the same day of the month.
- [WEEKDAY](https://spreadsheetpractice.com/functions/weekday): WEEKDAY returns the day of the week for a date as a number.

## Questions

### How do I add business days to a date in Excel?

Use =WORKDAY(A2,10) to move 10 working days forward, skipping weekends. Add a holiday range as the third argument.

### Does WORKDAY count the start date?

No. It starts counting from the next working day, so WORKDAY(A2,1) is the first business day after A2.

### Can WORKDAY skip a different weekend, like Friday and Saturday?

Not WORKDAY itself. WORKDAY.INTL takes a weekend argument for that.

## Practice

A graded WORKDAY exercise ("Ship dates") is on [the WORKDAY page](https://spreadsheetpractice.com/functions/workday). It is checked instantly, then re-checked on changed data.

---